TITEN HD® Heavy Duty Screw Anchor for Cracked and Uncracked Concrete

Load-Adjustment Factors in Face-of-Wall Installation in 8" Grout-Filled CMU:

Edge Distance and Spacing, Tension and Shear Loads

 
caution!These tables are not for use with SD design methods

How to use these charts:

  1. The following tables are for reduced end and edge distance and spacing.
  2. Locate the anchor size to be used for either a tension and/or
    shear load application.
  3. Locate the embedment (E) at which the anchor is to be installed.
  4. Locate the end or edge distance (Cact) or spacing (Sact) at which the
    anchor is to be installed.
  5. The load-adjustment factor (fc or fs) is the intersection of the row and column.
  6. Multiply the allowable load by the applicable load-adjustment factor.
  7. Reduction factors for multiple edges or spacings are multiplied together.
Tension Load Concrete Block (CMU) Concrete Block (CMU)

Edge or End Distance Tension (fc)

Edge Distance Tension
Tension Load Concrete Block (CMU) Concrete Block (CMU)
Edge and End Distance Shear (fc) Shear Load Parallel to Edge or End

End Distance Shear - Shear Load Parallel to Edge or End

  1. E = Embedment depth (inches).
  2. Cact = actual end or edge distance at which anchor is installed (inches).
  3. Ccr = critical end or edge distance for 100% load (inches).
  4. Cmin = minimum end or edge distance for reduced load (inches).
  5. fc = adjustment factor for allowable load at actual end or edge distance.
  6. fccr = adjustment factor for allowable load at critical end or edge distance. fccr is always = 1.00.
  7. fcmin = adjustment factor for allowable load at minimum end or edge distance.
  8. fc = fcmin + [(1 - fcmin) (Cact - Cmin) / (Ccr - Cmin)].

Tension Load Concrete Block (CMU) Concrete Block (CMU)
End and Edge Distance Shear (fc) Shear Load Perpendicular to Edge or End (Directed Toward Edge or End)

End and Edge Distance Shear
End and Edge Distance Shear (fc) Shear Load Perpendicular to Edge or End (Directed Away From Edge or End)

End and Edge Distance Shear

  1. E = Embedment depth (inches).
  2. Cact = actual end or edge distance at which anchor is installed (inches).
  3. Ccr = critical end or edge distance for 100% load (inches).
  4. Cmin = minimum end or edge distance for reduced load (inches).
  5. fc = adjustment factor for allowable load at actual end or edge distance.
  6. fccr = adjustment factor for allowable load at critical end or edge distance. fccr is always = 1.00.
  7. fcmin = adjustment factor for allowable load at minimum end or edge distance.
  8. fc = fcmin + [(1 - fcmin) (Cact - Cmin) / (Ccr - Cmin)].

Spacing Tension (fs)

Spacing Tension
Tension Load Concrete Block (CMU) Concrete Block (CMU)
Spacing Shear (fs)

Spacing Shear

  1. E = Embedment depth (inches).
  2. Sact = actual spacing distance at which anchors are installed (inches).
  3. Scr = critical spacing distance for 100% load (inches).
  4. Smin = minimum spacing distance for reduced load (inches).
  5. fs = adjustment factor for allowable load at actual spacing distance.
  6. fscr = adjustment factor for allowable load at critical spacing distance. fscr is always = 1.00.
  7. fsmin = adjustment factor for allowable load at minimum spacing distance.
  8. fs = fsmin + [(1 - fsmin) (Sact - Smin) / (Scr - Smin)].


Home | About Simpson Strong-Tie | Contact Simpson Strong-Tie | Browse Products | Product Use Information
Privacy Policy | User Agreement | Limited Warranty | Parent Company

Stay informed! Sign up for Simpson Strong-Tie newsletters

Copyright © 2012, Simpson Strong-Tie Company Inc. All Rights Reserved
Contact Webmaster with questions or comments.

Printed from
© 2012 Simpson Strong-Tie®