Column with Standard Base Plate Installation Sequence

Strong Frame Moment Frame

  1. Locate column line by using centerline of anchorage template.
  2. Install anchorage kit for each column and place concrete footing.
  3. Remove anchorage template (MFTPL) and reinstall four (4) leveling nuts.
  4. Lower columns onto anchor bolts.
  5. Level columns by raising or lowering the leveling nuts under base plate.
  6. Secure columns in place by tightening the nuts above base plate, provided with columns.
  7. Place 5,000 psi (min.) non-shrink grout under base plate prior to loading frame.

Refer to Strong Frame Installation for additional frame installation information.